Engineer's Opinion of Probable Cause

The cost of implementing this project has been estimated by using cost averages in the Flagstaff area. The earthwork cut quantities are a total cost of $0 as the soil on site is assumed to have no value. As seen in the last row, a contingency is applied to the projected total cost to cover unforeseen issues and conditions.