Schedule / Resources / Budget

Capstone I roadmap, Spring 2026 major events, and current budget stance.

Schedule — Outcome-Focused Roadmap

Window Milestone External-Facing Outcome
Sept M1 — Project Framing One-page brief: problem, target users, success criteria, initial risks.
Late Sept M2 — Tech Feasibility Spike Working tech spike proving GPS + web map SDK integration (desktop & mobile browser).
Early Oct M3 — Prototype A (Navigation) Clickable prototype with live location, target pins, and route hints. Short demo video (≤90s).
Mid Oct M4 — Prototype B (Accessible UI) Refined UI components (contrast-safe, keyboard-navigable). 5-min usability smoke test notes.
Late Oct M5 — Nationwide POIs (Overpass/Wikidata) Automated ingestion pipeline syncing POIs from Overpass + Wikidata APIs and caching them for launch.
Early Nov M6 — Alpha Demo Alpha build walkthrough with 1 guided mission; feedback from at least 2 non-team users.
Mid Nov M7 — Beta Readiness Stabilized features, instrumented basic metrics (time-to-target); issue backlog triaged.
Late Nov M8 — Public Tech Demo Live demo + short video posted; risks & next-semester plan published on website.
Dec M9 — Site V1 Employer-ready website: overview, video, screenshots, tech notes, and contact.
Spring (Capstone II) M10 — Build & Delivery Alpha Demo I/II, Design Reviews 2/3, UGRADS poster/oral milestones, Acceptance Demo, Final Website, and final product handoff.

Schedule — Capstone II (Spring 2026)

Weeks Major Event Key Deliverables / Due Items
Weeks 1-2 Capstone Kickoff Alpha Demo I flight plan, and Communication Strategy Memo.
Weeks 3-4 Software Design Prep Design Document milestone and initial prep for the Design Review 2 presentation.
Week 5 Alpha Demonstration I Alpha Demo I plus Alpha Demo II flight-plan prep.
Week 6 Design Review 2 Presentation Design Review 2 Presentation and Peer Eval #1. UGRADS registration work begins and the team website continues evolving.
Weeks 7-8 Testing & UGRADS Registration Design Document Final, Software Testing Plan work, and UGRADS Registration Form.
Week 9 Alpha Demonstration II Alpha Demo II mentor deadline, Acceptance Demo flight plan, and Software Testing Plan.
Week 10 Design Review 3 Presentation Design Review 3 Presentation and Peer Eval #2. UGRADS Poster production starts.
Weeks 11-13 UGRADS Poster & Oral Prep UGRADS Poster, UGRADS Oral Presentation Dry Run
Week 14 UGRADS Conference UGRADS Oral Presentation schedule and Peer Eval #3. Final Report and Product Delivery ramp up.
Weeks 15-16 Acceptance Demo & Final Delivery Acceptance Demo, Final Website and Course Evaluation

Heads up: After the Acceptance Demo, the client must sign the user manual and product check-off sheet before final product delivery closes out.

Resources (Minimal)

  • Team: 4 developers (John Zeledon, Mitchell Morris, Hunter Beach, Tristen Calder)
  • Tooling: GitHub (private repo, PR reviews), JetBrains IDEs, VS Code as needed
  • Hosting: NAU Capstone archival server (static site)
  • Devices: Personal computers as well as Android and iOS mobile phones for on-device testing
  • Maps/API: Web map SDK (vendor TBD following cost/limits review)

Budget

No budget at this time. We plan to use free academic tiers and open-source tooling. Any future costs (e.g., commercial map SDK usage above free tier) will be reviewed with our sponsor before adoption.