Team E Meeting Minutes
Wednesday, October
20, 1999
Scott’s Office
3:00pm
In Attendance at 3:00pm:
Scott Hancock, Vishal Golia, Greg Sitrick, and Donnie Yazzie.
Greg will email Dataforth 2 dates as a possibility to visit their facilities. The two dates are 11/5/99 and 11/12/99.
On 10/21/99 Scott will send the requirements document, the design plan, and the project schedule to Lee Payne.
Greg will plot simulations of the strain gauge next week.
Vishal will research the microprocessor and find out how to get the necessary software.
Donnie will decide which ADC and DAC to use.
Scott will determine communications between the parts and the host. He will also finalize the web page.