The following project table is a planned schedule for spring semester, 2000.
| Work Tasks | Planned Start | Planned Complete |
| 1. Finish Proposal | ||
| Specs | finished | finished |
| Research | finished | finished |
| Schedule | wk1, d2 | wk1, d4 |
| Architecture | wk1,d2 | wk1, d5 |
| 2. Validate with Sponsor: | ||
| Meet with Sponsor | wk2,d3 | wk2,d3 |
| Validate Web-site | wk2,d1 | wk2,d3 |
| 3. Do Detailed Software Design | ||
| Data | wk2,d4 | wk2 d6 |
| Processes | wk3,d1 | wk3,d3 |
| Objects | wk3,d3 | wk3,d5 |
| 4. Coding and Implementation | ||
| Interface Class and Headers | wk4,d1 | wk4,d3 |
| PPF_Logic Prototype | wk4,d3 | wk5,d3 |
| Parallel_Wrapper | wk5,d1 | wk6,d1 |
| PPF_Logic with Wrapper | wk6,d1 | wk7,d3 |
| Statistics and Timer | wk7,d3 | wk8,d1 |
| 5. Finish Code | ||
| Testing | wk8,d1 | wk10,d5 |
| Revision | wk8,d1 | wk10,d5 |
| Review | wk8,d1 | wk10,d5 |
| 6. Finish documentation | ||
| Code Documentation | wk11,d1 | wk11,d5 |
| Project Usage Documentation | wk11,d1 | wk11,d5 |