STATUS REPORT 27 Feb 1998
TASKS COMPLETED
-
In preparation for the test document, the team compiled a complete algoritmic description of GNAT.
-
In the process of compiling the algorithmic description, changes were made in the OMT. Other parts of the code, the GUI, Lists, and Display routines, were optimized and standardized.
-
The first Status review was scheduled for Thursday, Mar 5, at 1 p.m.. This time was confirmed with Richard Ames.
TASKS CONTINUING
-
All team members have returned to coding, aided by their problem descriptions.
TASKS DELAYED
-
Implementing the network has been put on hold.
INDIVIDUAL TASKS
-
Matt Petro developed the test plan for the GNAT GUI.
-
Matt Ericson developed the test plan for the LIST module.
-
Rob Waltz developed the test plan for the DISPLAY and STATISTICS modules.
-
John Kobinski developed the test plan for the SNOOP module.
-
Rob Waltz developed the test plan for Integration #1: LIST, DISPLAY and STATISTICS modules.
-
Matt Ericson developed the test plan for Integration #2: Integration #1 and SNOOP module.
-
Matt Petro developed the test plan for Integration #3: Integration #2 and the GUI.
-
Matt Petro formatted the test plan document to standardize everyone's test plans.
TASKS STARTED
-
The team has started preparing an agenda for the first Status review.
-
Rob Waltz will update the OMT to reflect design changes.
-
Matt Petro will update the schedule to reflect current status.
-
All team members will continue to code their modules.
HOURS
Matt Ericson |
27 hours |
John Kobinski |
20 hours |
Matt Petro |
28 hours |
Rob Waltz |
33 hours |