STATUS REPORT 5 Dec 1997

TASKS FINISHED

  1. Reviews - All team members submitted their projects for team review

TASKS CONTINUING

  1. Matt Ericson and Rob Waltz are putting the finishing touches on the Works-Like prototype
  2. Matt Petro is encorporating team recommendations into the design document
  3. John Kobinski has prepared the team notebook (with the exception of the design document) and is validating the links in the website.
  4. Rob Waltz is updating the OMT docs

TASKS DELAYED

None

TASKS STARTED

None

HOURS

Matt Ericson 35 hours
John Kobinski 20 hours
Matt Petro 28 hours
Rob Waltz 38 hours
 

INDIVIDUAL ACHIEVEMENT

  1. John Kobinski updated the notebook
  2. Matt Ericson and Rob Waltz spent many hours getting the prototype to parse a Snoop file.
  3. Matt Petro created a preliminary design document, including schedules, testing procedures, and OMT explanations.
  4. Rob Waltz revamped the OMT to reflect design changes.
  5. Matt Ericson added several options to the works like prototype.
  6. John Kobinski incorporated the necessary material into the website, which passed team review with flying colors.