STATUS REPORT 3 Oct 1997

TASKS COMPLETED

  1. Specifications document (pending approval from Dr. Collier and Rich Ames)

TASKS PENDING

  1. Continued to revise schedule.
  2. The Microprocessor lab has been rekeyed and Matt Ericson has put in the paperwork for a key.
  3. Matt Ericson has implemented a web page prototype and it is under review by the design team.
  4. Matt Ericson and Matt Petro are writing the project proposal.

TASKS DELAYED

  1. Setting up a test network is waiting on the Microprocessor lab key.

TASKS STARTED

  1. John Kobinski and Rob Waltz are designing the intial "looks-like" prototype for the GUI.

HOURS

Matt Ericson 8 hours
John Kobinski 9 hours
Matt Petro 10 hours
Rob Waltz 9 hours
 

ISSUES

  1. The team has e-mailed Rich Ames with a request for US Software to provide a copy of the Visual C++ software package and some documentation.