STATUS REPORT 10 Oct 1997

TASKS COMPLETED

  1. Revision of specs document
  2. Completion and submittal of preliminary project proposal
  3. Completion and submittal of final project proposal

TASKS CONTINUING

  1. Website design
  2. Further revision of specs document

TASKS DELAYED

  1. Set up of network

TASKS INITIATED

  1. Preliminary "looks-like" prototype design

HOURS

Matt Ericson 15 hours
John Kobinski 10 hours
Matt Petro 10 hours
Rob Waltz 7 hours
 

INDIVIDUAL ACHIEVEMENT

Matt Ericson

  1. Worked on project proposal
  2. Obtained key for Micro lab
  3. Worked on Web page
  4. Worked on prototype

John Kobinski

  1. Worked on Specs revision
  2. Researched Visual C++
  3. Worked on prototype

Matt Petro

  1. Worked on project proposal
  2. Worked on Specs doc
  3. Worked on prototype

Rob Waltz

  1. Worked on prototype
  2. Worked on Specs doc