Name |
Duration |
Start |
Finish |
Percent Complete |
Predecessors |
Resource Names |
Packet Reference class | 42.00d | Sun 1/25/98 | Sat 3/7/98 | 100% | | Matt Ericson |
__Coding | 3.00d | Sun 1/25/98 | Tue 1/27/98 | 100% | | Matt Ericson |
__Unit Test | 4.00d | Wed 3/4/98 | Sat 3/7/98 | 100% | 2 | Matt Ericson |
Packet class | 42.00d | Sun 1/25/98 | Sat 3/7/98 | 100% | | Matt Ericson |
__Coding | 3.00d | Sun 1/25/98 | Tue 1/27/98 | 100% | | Matt Ericson |
__Unit Test | 4.00d | Wed 3/4/98 | Sat 3/7/98 | 100% | 5 | Matt Ericson |
Connection class | 21.00d | Sun 2/15/98 | Sat 3/7/98 | 100% | | Matt Ericson |
__Coding | 7.00d | Sun 2/15/98 | Sun 2/22/98 | 100% | | Matt Ericson |
__Unit Test | 4.00d | Wed 3/4/98 | Sat 3/7/98 | 100% | 8 | Matt Ericson |
List support classes thread | 7.00d | Sun 3/8/98 | Sat 3/14/98 | 100% | 1,4,7 | John Kobinski |
__Integration | 2.00d | Sun 3/8/98 | Mon 3/9/98 | 100% | | John Kobinski |
__Integration Test | 5.00d | Tue 3/10/98 | Sat 3/14/98 | 100% | 11 | John Kobinski |
Pass packet | 28.00d | Sun 2/8/98 | Sat 3/7/98 | 100% | | John Kobinski,Matt Petro |
__Coding | 17.00d | Sun 2/8/98 | Tue 2/24/98 | 100% | | John Kobinski,Matt Petro |
__Unit Test | 11.00d | Wed 2/25/98 | Sat 3/7/98 | 100% | 14 | John Kobinski,Matt Petro |
Parse Snoop file | 28.00d | Sun 2/8/98 | Sat 3/7/98 | 100% | | John Kobinski,Matt Petro |
__Coding | 17.00d | Sun 2/8/98 | Tue 2/24/98 | 100% | | John Kobinski,Matt Petro |
__Unit Test | 11.00d | Wed 2/25/98 | Sat 3/7/98 | 100% | 17 | John Kobinski,Matt Petro |
Detect retransmissions | 28.00d | Sun 2/8/98 | Sat 3/7/98 | 100% | | John Kobinski,Matt Petro |
__Coding | 17.00d | Sun 2/8/98 | Tue 2/24/98 | 100% | | John Kobinski,Matt Petro |
__Unit Test | 11.00d | Wed 2/25/98 | Sat 3/7/98 | 100% | 20 | John Kobinski,Matt Petro |
BUILD 1 - Snoop class | 21.00d | Sun 3/15/98 | Sat 4/4/98 | 100% | 13,16,10,19 | Matt Ericson |
__Integration | 7.00d | Sun 3/15/98 | Sat 3/21/98 | 100% | | Matt Ericson |
__Integration Test | 14.00d | Sun 3/22/98 | Sat 4/4/98 | 100% | 23 | Matt Ericson |
CheckSums class | 28.00d | Sun 2/8/98 | Sat 3/7/98 | 100% | | Matt Ericson |
__Coding | 17.00d | Sun 2/8/98 | Tue 2/24/98 | 100% | | Matt Ericson |
__Unit Test | 11.00d | Wed 2/25/98 | Sat 3/7/98 | 100% | 26 | Matt Ericson |
ZeroWindow class | 28.00d | Sun 2/8/98 | Sat 3/7/98 | 100% | | Matt Ericson |
__Coding | 17.00d | Sun 2/8/98 | Tue 2/24/98 | 100% | | Matt Ericson |
__Unit Test | 11.00d | Wed 2/25/98 | Sat 3/7/98 | 100% | 29 | Matt Ericson |
Retransmissions class | 28.00d | Sun 2/8/98 | Sat 3/7/98 | 100% | | Matt Ericson |
__Coding | 17.00d | Sun 2/8/98 | Tue 2/24/98 | 100% | | Matt Ericson |
__Unit Test | 11.00d | Wed 2/25/98 | Sat 3/7/98 | 100% | 32 | Matt Ericson |
BUILD 2 - List classes | 21.00d | Sun 3/15/98 | Sat 4/4/98 | 100% | 25,28,10,31 | Matt Petro |
__Intgration | 7.00d | Sun 3/15/98 | Sat 3/21/98 | 100% | | Matt Petro |
__Integration Test | 14.00d | Sun 3/22/98 | Sat 4/4/98 | 100% | 35 | Matt Petro |
Dipslay bar graph | 21.00d | Sun 2/8/98 | Sat 2/28/98 | 100% | | Rob Waltz |
__Coding | 14.00d | Sun 2/8/98 | Sat 2/21/98 | 100% | | Rob Waltz |
__Unit Test | 7.00d | Sun 2/22/98 | Sat 2/28/98 | 100% | 38 | Rob Waltz |
Display line graph | 21.00d | Sun 2/8/98 | Sat 2/28/98 | 100% | | Rob Waltz |
__Coding | 14.00d | Sun 2/8/98 | Sat 2/21/98 | 100% | | Rob Waltz |
__Unit Test | 7.00d | Sun 2/22/98 | Sat 2/28/98 | 100% | 41 | Rob Waltz |
Display histogram | 21.00d | Sun 2/8/98 | Sat 2/28/98 | 100% | | Rob Waltz |
__Coding | 14.00d | Sun 2/8/98 | Sat 2/21/98 | 100% | | Rob Waltz |
__Unit Test | 7.00d | Sun 2/22/98 | Sat 2/28/98 | 100% | 44 | Rob Waltz |
Display pie chart | 21.00d | Sun 2/8/98 | Sat 2/28/98 | 100% | | Rob Waltz |
__Coding | 14.00d | Sun 2/8/98 | Sat 2/21/98 | 100% | | Rob Waltz |
__Unit Test | 7.00d | Sun 2/22/98 | Sat 2/28/98 | 100% | 47 | Rob Waltz |
Graphic display | 7.00d | Sun 3/1/98 | Sat 3/7/98 | 100% | 37,40,43,46 | Rob Waltz |
__Integration | 3.00d | Sun 3/1/98 | Tue 3/3/98 | 100% | | Rob Waltz |
__Integration Test | 4.00d | Wed 3/4/98 | Sat 3/7/98 | 100% | 50 | Rob Waltz |
Text list display | 7.00d | Sun 3/1/98 | Sat 3/7/98 | 100% | | Rob Waltz |
__Integration | 3.00d | Sun 3/1/98 | Tue 3/3/98 | 100% | | Rob Waltz |
__Integration Test | 4.00d | Wed 3/4/98 | Sat 3/7/98 | 100% | 53 | Rob Waltz |
BUILD 3 - GUI display | 21.00d | Sun 3/8/98 | Sat 3/28/98 | 100% | 49,52 | Matt Ericson |
__Integration | 7.00d | Sun 3/8/98 | Sat 3/14/98 | 100% | | Matt Ericson |
__Integration Test | 14.00d | Sun 3/15/98 | Sat 3/28/98 | 100% | 56 | Matt Ericson |
Write packet | 14.00d | Sun 3/1/98 | Sat 3/14/98 | 100% | | Rob Waltz |
__Coding | 7.00d | Sun 3/1/98 | Sat 3/7/98 | 100% | | Rob Waltz |
__Unit Test | 7.00d | Sun 3/8/98 | Sat 3/14/98 | 100% | 59 | Rob Waltz |
Write statistical data | 14.00d | Sun 3/1/98 | Sat 3/14/98 | 100% | | Rob Waltz |
__Coding | 7.00d | Sun 3/1/98 | Sat 3/7/98 | 100% | | Rob Waltz |
__Unit Test | 7.00d | Sun 3/8/98 | Sat 3/14/98 | 100% | 62 | Rob Waltz |
Outputfile class | 14.00d | Sun 3/15/98 | Sat 3/28/98 | 100% | 58,61 | Rob Waltz |
__Integration | 3.00d | Sun 3/15/98 | Tue 3/17/98 | 100% | | Rob Waltz |
__Integration Test | 11.00d | Wed 3/18/98 | Sat 3/28/98 | 100% | 65 | Rob Waltz |
BUILD 4 - Final build | 24.00d | Sun 4/5/98 | Tue 4/28/98 | 100% | 55,64,34,22 | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
__System integration | 10.00d | Sun 4/5/98 | Tue 4/14/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
__System test | 14.00d | Wed 4/15/98 | Tue 4/28/98 | 100% | 68 | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
Detailed Development Schdule | 14.00d | Thu 1/15/98 | Wed 1/28/98 | 100% | | |
__Task Layout | 9.00d | Thu 1/15/98 | Fri 1/23/98 | 100% | | Matt Petro |
__Resource Assignment | 5.00d | Sat 1/24/98 | Wed 1/28/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
Detailed Development Schedule | 1.00d | Thu 1/29/98 | Thu 1/29/98 | 100% | 70 | |
Coding Standards Document | 7.00d | Thu 1/22/98 | Wed 1/28/98 | 100% | | Matt Ericson,Rob Waltz |
Detailed Test Plan | 25.00d | Fri 1/30/98 | Mon 2/23/98 | 100% | | |
__White Box Test Plans | 25.00d | Fri 1/30/98 | Mon 2/23/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
____Integration Test Plans | 13.00d | Fri 1/30/98 | Wed 2/11/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
____System Test Plans | 12.00d | Thu 2/12/98 | Mon 2/23/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
__Black Box Test Plans | 25.00d | Fri 1/30/98 | Mon 2/23/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
____Integration Test Plans | 13.00d | Fri 1/30/98 | Wed 2/11/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
____System Test Plans | 12.00d | Thu 2/12/98 | Mon 2/23/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
Detailed Test Plan | 1.00d | Tue 2/24/98 | Tue 2/24/98 | 100% | 75 | |
Formal Status Review | 1.00d | Thu 3/5/98 | Thu 3/5/98 | 100% | | |
Formal Technical Review | 1.00d | Tue 3/10/98 | Tue 3/10/98 | 100% | | |
Formal Technical Review | 1.00d | Tue 3/24/98 | Tue 3/24/98 | 100% | | |
Formal Technical Review | 1.00d | Tue 4/7/98 | Tue 4/7/98 | 100% | | |
Presentation Practice | 7.00d | Thu 4/9/98 | Wed 4/15/98 | 100% | | Matt Ericson,John Kobinski,Matt Petro,Rob Waltz |
Presentation Dry-run | 1.00d | Thu 4/16/98 | Thu 4/16/98 | 100% | 87 | |
Design Conference | 1.00d | Fri 4/24/98 | Fri 4/24/98 | 100% | | |
As-built report prep | 19.00d | Sat 4/11/98 | Wed 4/29/98 | 100% | | Matt Petro |
As-Built Report | 1.00d | Thu 4/30/98 | Thu 4/30/98 | 100% | 90 | |
Software Release | 1.00d | Thu 4/30/98 | Thu 4/30/98 | 100% | | |
Web site update | 1.00d | Sun 2/1/98 | Sun 2/1/98 | 100% | | Matt Petro |
Web site update | 1.00d | Sun 2/15/98 | Sun 2/15/98 | 100% | | Matt Petro |
Web site update | 1.00d | Sun 3/1/98 | Sun 3/1/98 | 100% | | Matt Petro |
Web site update | 1.00d | Sun 3/15/98 | Sun 3/15/98 | 100% | | Matt Petro |
Web site update | 1.00d | Sun 3/29/98 | Sun 3/29/98 | 100% | | Matt Petro |
Web site update | 1.00d | Sun 4/12/98 | Sun 4/12/98 | 100% | | Matt Petro |
Web site update | 2.00d | Tue 4/28/98 | Wed 4/29/98 | 100% | | Matt Petro |
Notebook update | 1.00d | Sun 2/1/98 | Mon 2/2/98 | 100% | | John Kobinski |
Notebook update | 1.00d | Sun 2/15/98 | Sun 2/15/98 | 100% | | John Kobinski |
Notebook update | 1.00d | Sun 3/1/98 | Sun 3/1/98 | 100% | | John Kobinski |
Notebook update | 1.00d | Sun 3/15/98 | Sun 3/15/98 | 100% | | John Kobinski |
Notebook update | 1.00d | Sun 3/29/98 | Sun 3/29/98 | 100% | | John Kobinski |
Notebook update | 1.00d | Sun 4/12/98 | Sun 4/12/98 | 100% | | John Kobinski |
Notebook update | 2.00d | Tue 4/28/98 | Wed 4/29/98 | 100% | | John Kobinski |